Multiple Choice
Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to
A) assign each TBC at the start of its work package.
B) assign each TBC at the end of its work package.
C) distribute each TBC over the project by dividing the total by the number of work packages and assigning that amount to each.
D) distribute each TBC over the duration of its work package.