Multiple Choice
The cumulative earned value of the project is
A) the sum of the planned costs of the project
B) the sum of the budgeted costs of the work actually performed.
C) the sum of the budgeted cost of the work scheduled.
D) the sum of the differences between what was planned and the actual costs.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q51: Costs are _ when an item is
Q52: Allocating total project costs for the various
Q53: The percent complete estimate for a work
Q54: The _ is the amount that was
Q55: The budget for each work package is<br>A)
Q57: Once a total budgeted cost has been
Q58: The _ is the product of the
Q59: Facilities costs in the project costs estimate
Q60: What is the cost performance index for
Q61: The _ for the entire project or