Multiple Choice
If the cumulative earned value is $10 and the cumulative actual costs are $20, then the CPI is
A) $10.
B) -$10.
C) 0.5.
D) 2.0.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q37: Travel costs in the project costs estimate
Q38: The forecasted cost at completion is<br>A) a
Q39: The key to effective cost control is
Q40: The _ is the amount that is
Q41: Committed costs in a project are<br>A) those
Q43: Cost estimates should be unreasonable and excessive.
Q44: In many projects, large dollar amounts are
Q45: Often, the sum of the initial estimated
Q46: The to-complete performance index is<br>A) the amount
Q47: The actual cost on a project is<br>A)