Multiple Choice
The to-complete performance index is
A) the amount of funds remaining for the project.
B) the rate of performance required for the remaining work to finish the project within budget.
C) the ratio of committed costs remaining to planned costs.
D) the ratio of planned costs for the work remaining to the budgeted costs of the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q41: Committed costs in a project are<br>A) those
Q42: If the cumulative earned value is $10
Q43: Cost estimates should be unreasonable and excessive.
Q44: In many projects, large dollar amounts are
Q45: Often, the sum of the initial estimated
Q47: The actual cost on a project is<br>A)
Q48: A second method for determining the forecasted
Q49: The _ is the amount that was
Q50: To keep track of _, it's necessary
Q51: Costs are _ when an item is