Solved

The Actual Cost on a Project Is

Question 47

Multiple Choice

The actual cost on a project is


A) the planned amount to be spent on the project plus unexpected costs
B) the sum of the budgeted costs.
C) the amount of funds expended on the project.
D) the total of the unexpected costs.

Correct Answer:

verifed

Verified

Unlock this answer now