Solved

A Second Method for Determining the Forecasted Cost at Completion

Question 48

Multiple Choice

A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget.If the cumulative actual cost is greater than the cumulative earned value, then


A) the FCAC is greater than the TBC.
B) the FCAC is less than the TBC.
C) the FCAC cannot be calculated with the values given.
D) additional information is needed to predict the FCAC.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions