Multiple Choice
Which of the following is not a way to reduce the costs of activities:
A) reduce the scope or requirements.
B) substitute less expensive materials.
C) assign a person with less expertise or less experience to perform or help with the activity.
D) increase productivity through improved methods or technology.
Correct Answer:

Verified
Correct Answer:
Verified
Q66: The worst scenario from the contractor's point
Q67: Committed costs are also known as discharged
Q68: _ is the difference between the cumulative
Q69: The total budgeted cost for the project
Q70: Determining the earned value involves collecting data
Q72: The contractor might try to negotiate payment
Q73: Once the project starts, it is necessary
Q74: Another indicator of cost performance is cost
Q75: The key to managing a cash flow
Q76: The _ is the amount that was