Once the project starts, it is necessary to keep track of actual cost and committed cost so that they can be compared to the ____.
A) total budgeted cost
B) cumulative budgeted cost
C) total cumulative fees
D) contract cumulating amount
Correct Answer:

Verified
Correct Answer:
Verified