Multiple Choice
Determining the earned value involves collecting data on the percent complete for each work package and then converting this percentage to a dollar amount by multiplying the ____ of the work package by the percent complete.
A) total budgeted cost
B) cumulative budgeted cost
C) total cumulative fees
D) contract cumulating amount
Correct Answer:

Verified
Correct Answer:
Verified
Q65: The cost performance analysis should include identifying
Q66: The worst scenario from the contractor's point
Q67: Committed costs are also known as discharged
Q68: _ is the difference between the cumulative
Q69: The total budgeted cost for the project
Q71: Which of the following is not a
Q72: The contractor might try to negotiate payment
Q73: Once the project starts, it is necessary
Q74: Another indicator of cost performance is cost
Q75: The key to managing a cash flow