Multiple Choice
The two-step process for budgeting is
A) estimate the aggregate cost for the activity and distribute the costs over the expected time span.
B) determine the costs and add on contingency amounts.
C) examine past projects that are similar and estimate the amount for the current project.
D) determine the amount of money available from the sponsor and distribute it across the project time required.
Correct Answer:

Verified
Correct Answer:
Verified
Q58: The _ is the product of the
Q59: Facilities costs in the project costs estimate
Q60: What is the cost performance index for
Q61: The _ for the entire project or
Q62: At the beginning of the project, it
Q64: When the CPI goes below 1.0 or
Q65: The cost performance analysis should include identifying
Q66: The worst scenario from the contractor's point
Q67: Committed costs are also known as discharged
Q68: _ is the difference between the cumulative