Multiple Choice
At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy.This is especially true for
A) projects with a short term.
B) longer-term projects.
C) projects that are similar to ones completed by the organization before.
D) projects with activities that are serially related.
Correct Answer:

Verified
Correct Answer:
Verified