Multiple Choice
What is the cost performance index for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000.
A) CPI = 1.25
B) CPI = 0.8
C) CPI = 1.1
D) CPI = 0.91
Correct Answer:

Verified
Correct Answer:
Verified