Multiple Choice
A cost performance index greater than 1.0 means
A) for every dollar spent on the project, more than one dollar of earned value was received
B) for every dollar of earned value received, more than one dollar was spent on the project
C) corrective action should be taken on the project.
D) the total actual costs exceed the total budgeted costs
Correct Answer:

Verified
Correct Answer:
Verified