____ Involves the Following: Analyzing Cost Performance to Determine Which

Question 77

Multiple Choice

____ involves the following: Analyzing cost performance to determine which work packages may require corrective action; Deciding what specific corrective action should be taken; and Revising the project plan, including time and cost estimates, to incorporate the planned corrective action.


A) Resource analysis
B) CPI monitoring
C) Cost control
D) Problem solving