Multiple Choice
What is the cost variance for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000.
A) CV = - $2,000
B) CV = - $5,000
C) CV = $5,000
D) CV = $2,000