    Exam 7: Determining Costs, Budget and Earned Value
  5. Question
    What Is the Cost Variance for a Project That Has
Solved

What Is the Cost Variance for a Project That Has

Question 79

Question 79

Multiple Choice

What is the cost variance for a project that has a TBC = $50,000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000.


A) CV = - $2,000
B) CV = - $5,000
C) CV = $5,000
D) CV = $2,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q74: Another indicator of cost performance is cost

Q75: The key to managing a cash flow

Q76: The _ is the amount that was

Q77: _ involves the following: Analyzing cost performance

Q78: For a project, the TBC = $200,000,

Q80: A cost performance index greater than 1.0

Q81: The contractor's outflow of cash can be

Q82: The key to managing cash flow is

Q83: Based on analysis of actual cost it

Q84: Calculate the cost variance if the cumulative

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines