Multiple Choice
Free slack is the amount of time a specific activity can be
A) postponed without delaying the earliest start time of its immediately preceding activities.
B) postponed without delaying the earliest start time of its immediately succeeding activities.
C) accelerated without delaying the latest start time of its immediately succeeding activities.
D) accelerated without delaying the latest finish time of its immediately preceding activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q33: The project control process involves all of
Q34: The total completion time is 25 days.Task
Q35: Throughout a project, changes may occur that
Q36: One way to determine which activities make
Q37: Describe the agile project management for a
Q39: The actual finish time of an activity<br>A)
Q40: Latest start time is calculated by<br>A) subtracting
Q41: The overall window of time in which
Q42: Total Slack is sometimes called<br>A) drift.<br>B) ride.<br>C)
Q43: When considering the availability of resources, it