The actual finish time of an activity


A) is always less than the estimated duration.
B) has a ripple effect in the project and may alter the remaining activities' earliest start and finish times.
C) has no impact on the critical path of the project.
D) is used to calculate the latest start and finish times of the remaining activities in the project.

Correct Answer: