Multiple Choice
The overall window of time in which a project must be completed is defined by its ____ time and ____ time.
A) earliest start, earliest finish
B) latest start, latest finish
C) estimated start, required completion
D) critical, most critical
Correct Answer:

Verified
Correct Answer:
Verified