Multiple Choice
If ____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time.
A) total time
B) free time
C) total slack
D) cumulative slack
Correct Answer:

Verified
Correct Answer:
Verified