Each time the schedule is recalculated in the project, the schedule should be
A) analyzed to see if it needs further adjustment.
B) accelerated on all paths with a positive slack.
C) examined for a change in critical paths then fast track the new critical path.
D) examined and assign additional resources to the activities with free slack.
Correct Answer:

Verified
Correct Answer:
Verified