Multiple Choice
The key to effective project control is
A) assigning a specific resource to gather data from the project team.
B) measuring actual progress and comparing it to planned progress.
C) calculating the costs of the project.
D) communicating with the project sponsor and the stakeholders for the project.
Correct Answer:

Verified
Correct Answer:
Verified