When Changes Are Agreed Upon, a New ____ Should Be

Question 31

Multiple Choice

When changes are agreed upon, a new ____ should be established and used as the benchmark against which actual project performance will be compared.


A) time-cost diagram
B) baseline plan
C) work expectations form
D) management matrix