Multiple Choice
If the project is ahead of schedule, then concentrated efforts should be made to
A) allow the tasks to start on the days estimated as the earliest start time in the baseline plan.
B) fast track the critical path activities.
C) reduce the number of resources on the project because they are not needed.
D) keep it ahead of schedule.
Correct Answer:

Verified
Correct Answer:
Verified
Q27: The Scrum master is _ as a
Q28: As a part of the Scrum technique
Q29: The _ trade-off methodology is used to
Q30: The project team member also referred to
Q31: When changes are agreed upon, a new
Q33: The project control process involves all of
Q34: The total completion time is 25 days.Task
Q35: Throughout a project, changes may occur that
Q36: One way to determine which activities make
Q37: Describe the agile project management for a