    As a Part of the Scrum Technique in Agile Project
Solved

As a Part of the Scrum Technique in Agile Project

Question 28

Question 28

Multiple Choice

As a part of the Scrum technique in agile project management, a sprint is usually one to four


A) days.
B) minutes.
C) weeks.
D) months.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q23: The duration of a task is<br>A) the

Q24: The latest start time for a specific

Q25: Schedule updates of the project using actual

Q26: Agile project management is an approach to

Q27: The Scrum master is _ as a

Q29: The _ trade-off methodology is used to

Q30: The project team member also referred to

Q31: When changes are agreed upon, a new

Q32: If the project is ahead of schedule,

Q33: The project control process involves all of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines