Activities in a Network Diagram Have ____, That Is, They

Question 77

Multiple Choice

Activities in a network diagram have ____, that is, they are linked in a logical sequence to show which activities must be finished before others can start.


A) a serial order
B) a ladder order
C) an interrelated position
D) a dependent relationship

Correct Answer: