The WBS Should Be Decomposed to a Level That Identifies

Question 81

Multiple Choice

The WBS should be decomposed to a level that identifies individual work packages for


A) each person that planned the project.
B) each resource assigned to the project.
C) the level of detail specified by the customer.
D) each specific deliverable listed in the project scope document.

Correct Answer: