The following represents a project with four activities.All times are in weeks. Table 11-2 The following represents a project with four activities.All times are in weeks.   -According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )  A) 0.07 B) 0.93 C) 0.43 D) 0.77 E) None of the above
-According to Table 11-2,there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals. )


A) 0.07
B) 0.93
C) 0.43
D) 0.77
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions