Multiple Choice
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?
A) 108.0
B) 110.4
C) 89.6
D) 85.0
E) 100
Correct Answer:

Verified
Correct Answer:
Verified
Q38: Which of the following is not a
Q39: PERT assumes that the total completion time
Q40: Development of a new deluxe version of
Q41: Consider the following project schedule: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg"
Q44: In PERT,we assume that<br>A)the times to complete
Q45: The expected completion time and variance of
Q46: Consider a project that has an expected
Q47: The crash time of an activity represents<br>A)the
Q48: Table 11-2<br>The following represents a project with
Q131: Given the variability of the activity completion