Multiple Choice
Table 11-2
The following represents a project with four activities.All times are in weeks.
-According to the data in Table 11-2,what is the critical path?
A) A-B
B) A-C
C) B-D
D) A-B-C-D
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q43: Your company is considering submitting a bid
Q44: In PERT,we assume that<br>A)the times to complete
Q45: The expected completion time and variance of
Q46: Consider a project that has an expected
Q47: The crash time of an activity represents<br>A)the
Q49: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1
Q51: Table 11-1<br>The following represents a project with
Q52: Table 11-2<br>The following represents a project with
Q53: In a PERT network,the latest (activity)start time
Q68: Gantt charts contain information about the time