Multiple Choice
In PERT analysis,the probability of the optimistic time occurring should be on the order of
A) 1/2.
B) 1/3.
C) 1/6.
D) 1/10.
E) 1/100.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Activity B of a project has a
Q5: Given: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Given:
Q6: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="The
Q7: Table 11-4<br>The following represents a project with
Q8: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1
Q10: PERT often assumes that time estimates follow
Q11: Table 11-4<br>The following represents a project with
Q44: The three time estimates employed in PERT
Q123: The optimistic time is the greatest amount
Q135: In CPM, crashing an activity that is