Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 3,7,and 11 days respectively,compute the expected time for this activity.
A) 5
B) 6
C) 7
D) 12
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified