Multiple Choice
The value of work completed for an activity is determined by which of the following?
A) budgeted cost - actual cost
B) actual cost divided by budgeted cost
C) percentage of work completed multiplied by actual activity cost
D) percentage of work completed multiplied by budgeted activity cost
E) activity difference divided by budgeted cost
Correct Answer: