Essay
Consider the project with the following estimates for activity times and precedence relationships: (a)What is the expected duration of the project?
(b)What is the project variance?
(c)If the deadline of the project is 25 days,what is the probability of finishing the project on time?
Correct Answer:

Verified
(a)23
(b)3...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
(b)3...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q42: In a PERT analysis, how is the
Q85: With PERT, we are able to calculate
Q103: The expected time in PERT is<br>A)a weighted
Q105: The value of work completed for an
Q106: An alternative approach to project crashing is
Q108: Given an activity's optimistic,most likely,and pessimistic time
Q109: Table 11-4<br>The following represents a project with
Q111: In a PERT network,the earliest (activity)start time
Q112: Table 11-3 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-3
Q141: Given the assumptions in PERT, the probability