Question 49

Multiple Choice

Figure 11-1 Figure 11-1   -Given the network shown in Figure 11-1,assume that the completion of activity C is delayed by four days.What changes will take place? A) The critical path will change to: A-C-B-D-E-F-H. B) Activity F will be delayed by four days. C) Activity E will be delayed by four days. D) Activity G will be delayed by four days. E) None of the above
-Given the network shown in Figure 11-1,assume that the completion of activity C is delayed by four days.What changes will take place?


A) The critical path will change to: A-C-B-D-E-F-H.
B) Activity F will be delayed by four days.
C) Activity E will be delayed by four days.
D) Activity G will be delayed by four days.
E) None of the above