Multiple Choice
Figure 11-1
-Given the network shown in Figure 11-1,assume that the completion of activity C is delayed by four days.What changes will take place?
A) The critical path will change to: A-C-B-D-E-F-H.
B) Activity F will be delayed by four days.
C) Activity E will be delayed by four days.
D) Activity G will be delayed by four days.
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified