Essay
A project has an anticipated stream of annual net receipts of $20,000. Its life is 6 years. No salvage value is expected at the end of the 6 years. Compute the net present value of the project, if its price is $80,000 and the applicable discount rate is 9%.
Correct Answer:

Verified
The present value of $20,000 per year fo...View Answer