Multiple Choice
A worker is assigned three tasks,A,B,and C,each having a duration of 20 days.One approach to completing these tasks would be to focus on one at a time,complete it,and then move to the second,followed by the third.One multitasking approach would call for dividing each task into fifths and rotating from one to the other so that the first fifths of A,B,and C are completed before the second fifths of A,B,and C are completed (always in this order) and so on until the activities are finished.What is the difference in the average completion times for the multitasked activities?
A) There is no difference in completion times for the two approaches.
B) The multitasked activities take 15% longer.
C) The multitasked activities take 25% longer.
D) The multitasked activities take 40% longer.
Correct Answer:

Verified
Correct Answer:
Verified
Q92: In order to estimate completion of a
Q93: All five members of a project team
Q94: Critical Chain Project Management is based on
Q95: All five members of a project team
Q96: A project is represented by the activity
Q98: The buffers supplied to non-critical paths in
Q99: Describe the Deming funnel exercise and what
Q100: The first step in the TOC (Theory
Q101: All five members of a project team
Q102: An organization's budget estimating process routinely misses