All five members of a project team add 15% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 10% for his personal safety margin.Then,anticipating a cut by top management,he adds another 10% to his final project estimate.Much to his surprise,top management cuts 30% off his time estimate.How much of a cushion is now built into the project?


A) 13%
B) 7%
C) 5%
D) -3%