Multiple Choice
In order to estimate completion of a Gaussian,or lognormal,distributed activity time with a 90% or higher degree of confidence,the time may be overestimated by as much as:
A) 20%.
B) 80%.
C) 160%.
D) 200%.
Correct Answer:

Verified
Correct Answer: