Multiple Choice
A project consists of three activities with information as shown in the table. What is the overall standard deviation of the project?
A) 24
B) 18
C) 8.41
D) 4.24
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q21: Keith welds a one-fourth-inch diameter ball bearing
Q28: What is aggregated buffer and how can
Q71: Successful implementation of CCPM depends on first:<br>A)identifying
Q76: Your next project consists of 5 consecutive
Q88: Which statement about critical chain methodology is
Q89: A project consists of three activities with
Q95: A project is represented by the activity
Q96: Use the project information in the table
Q97: A project is represented by the activity
Q98: Use the project information in the table