menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 11: Critical Chain Project Scheduling
  5. Question
    A Project Consists of Three Activities with Information as Shown
Solved

A Project Consists of Three Activities with Information as Shown

Question 89

Question 89

Multiple Choice

A project consists of three activities with information as shown in the table. What is the overall standard deviation of the project? A project consists of three activities with information as shown in the table. What is the overall standard deviation of the project?   A)  8.00 B)  4.24 C)  2.82 D)  5.56


A) 8.00
B) 4.24
C) 2.82
D) 5.56

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q21: Keith welds a one-fourth-inch diameter ball bearing

Q28: What is aggregated buffer and how can

Q33: What are the five steps behind the

Q36: Describe three ways that project members routinely

Q38: Critical Chain Project Methodology _ risk for

Q71: Successful implementation of CCPM depends on first:<br>A)identifying

Q76: Your next project consists of 5 consecutive

Q88: Which statement about critical chain methodology is

Q94: A project consists of three activities with

Q108: Which of the following statements about CCPM

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines