Multiple Choice
Drum buffers are:
A) a safety margin separating different projects scheduled to use the same resource.
B) extra safety that is applied to a project immediately after the use of the constrained resource.
C) a constraint separating different projects that requires a common buffer.
D) extra safety that is applied to a project immediately before the use of the constrained resource.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: A(n)_ refers to a safety margin that
Q4: The _ syndrome describes the tendency to
Q5: A worker is assigned three tasks,A,B,and C,each
Q6: A project is represented by the activity
Q7: Which of the following statement is best?<br>A)The
Q9: Which of these is Parkinson's Law?<br>A)Don't put
Q10: An important departure from traditional project management
Q11: A project is represented by the activity
Q12: Use the project information in the table
Q83: The critical chain is usually the same