Multiple Choice
Which of the following statement is best?
A) The critical chain requires that all resource leveling be done before the critical chain can be identified.
B) The critical path usually jumps task dependency links.
C) The critical chain relies on task dependency and is discovered after the fact,once the network is laid out.
D) The critical chain is usually the same path as the critical path within an activity network.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: A project is represented by the activity
Q3: A(n)_ refers to a safety margin that
Q4: The _ syndrome describes the tendency to
Q5: A worker is assigned three tasks,A,B,and C,each
Q6: A project is represented by the activity
Q8: Drum buffers are:<br>A)a safety margin separating different
Q9: Which of these is Parkinson's Law?<br>A)Don't put
Q10: An important departure from traditional project management
Q11: A project is represented by the activity
Q12: Use the project information in the table