Solved

A Project Is Represented by the Activity Durations (In Days,estimated

Question 6

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology? A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology?   A) 0 B) 1 C) 2 D) 3


A) 0
B) 1
C) 2
D) 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions