Multiple Choice
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology?
A) 0
B) 1
C) 2
D) 3
Correct Answer:

Verified
Correct Answer:
Verified
Q1: All five members of a project team
Q2: A project is represented by the activity
Q3: A(n)_ refers to a safety margin that
Q4: The _ syndrome describes the tendency to
Q5: A worker is assigned three tasks,A,B,and C,each
Q7: Which of the following statement is best?<br>A)The
Q8: Drum buffers are:<br>A)a safety margin separating different
Q9: Which of these is Parkinson's Law?<br>A)Don't put
Q10: An important departure from traditional project management
Q11: A project is represented by the activity