menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    What Is the Late Finish Time for Activity D Given
Solved

What Is the Late Finish Time for Activity D Given

Question 28

Question 28

Multiple Choice

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table? What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?   A)  14 B)  13 C)  12 D)  11


A) 14
B) 13
C) 12
D) 11

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Activity Z has estimates a = 5,b

Q15: The late start time should be calculated

Q21: One of the defining points of a

Q23: Use the network diagram and activity lengths

Q29: The variance of an activity is given

Q31: Which of these statements about this network

Q59: An activity has a pessimistic time that

Q69: What are three methods of duration estimation

Q91: Prior to creating a network,it is important

Q103: An activity has an optimistic time estimate

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines