Multiple Choice
An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected duration of the activity?
A) 13 days
B) 13.5 days
C) 12 days
D) 12.5 days
Correct Answer:

Verified
Correct Answer:
Verified