menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Achieving Competitive Advantage Study Set 2
  4. Exam
    Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path
  5. Question
    An Activity Has an Optimistic Time Estimate of 7 Days,a
Solved

An Activity Has an Optimistic Time Estimate of 7 Days,a

Question 103

Question 103

Multiple Choice

An activity has an optimistic time estimate of 7 days,a most likely estimate of 12 days,and a pessimistic estimate of 20 days.What is the expected duration of the activity?


A) 13 days
B) 13.5 days
C) 12 days
D) 12.5 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q33: At a burst point in a backward

Q91: Draw a network of any size that

Q98: What is the slack time for Activity

Q99: One approach to reducing project length would

Q100: In order to reduce the length of

Q101: Project Test Bank is composed of activities

Q102: A gentleman farmer maniacally works on academic

Q106: There's an old saying,"The job is not

Q107: The least amount of float is found:<br>A)in

Q108: A project's duration can be reduced by:<br>A)shortening

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines