Multiple Choice
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time.If the activity variance is 10,what is the expected time?
A) about 10 days
B) about 14 days
C) about 19 days
D) about 23 days
Correct Answer:

Verified
Correct Answer:
Verified