menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    Use the Information in the Table to Determine the Early
Solved

Use the Information in the Table to Determine the Early

Question 74

Question 74

Multiple Choice

Use the information in the table to determine the early finish time for Activity D. Use the information in the table to determine the early finish time for Activity D.   A)  day 23 B)  day 26 C)  day 29 D)  day 32


A) day 23
B) day 26
C) day 29
D) day 32

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q45: _ activities have two or more immediate

Q69: A project has the precedence requirements and

Q71: Project Test Bank is composed of activities

Q72: What is the slack time for Activity

Q78: Use the network diagram and activity lengths

Q79: What is the late start time for

Q81: In assigning a value for the most

Q85: Hammock activities break a task into greater

Q106: There's an old saying,"The job is not

Q116: The longest route through the network is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines