Question 61
True/False
Float is always measured in exactly the same way as slack.
Question 62
Multiple Choice
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
Question 63
Essay
Draw a network of any size that has at least one of each of the following features: merge activity, burst activity, hammock activity, ladder activity, critical path, serial activities, concurrent activities, critical path, and float. Mark these features on your network.
Question 64
Multiple Choice
A sequence of activities defined by the project network logic is a(n) :
Question 65
Multiple Choice
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?
Question 66
Multiple Choice
An activity has an optimistic time estimate of 7 days, a most likely estimate of 12 days, and a pessimistic estimate of 20 days. What is the expected standard deviation of the activity?