Multiple Choice
Use the information in the table to determine the late finish time for Activity B.
A) day 17
B) day 26
C) day 20
D) day 23
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q26: A sequence of activities defined by the
Q45: _ activities have two or more immediate
Q63: Draw a network of any size that
Q65: A backward pass is performed when it
Q65: What is the late start time for
Q67: An activity has an optimistic time estimate
Q69: A project has the precedence requirements and
Q71: Project Test Bank is composed of activities
Q72: What is the slack time for Activity
Q81: In assigning a value for the most