menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    Use the Information in the Table to Determine the Late
Solved

Use the Information in the Table to Determine the Late

Question 68

Question 68

Multiple Choice

Use the information in the table to determine the late finish time for Activity B. Use the information in the table to determine the late finish time for Activity B.   A)  day 17 B)  day 26 C)  day 20 D)  day 23


A) day 17
B) day 26
C) day 20
D) day 23

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q26: A sequence of activities defined by the

Q45: _ activities have two or more immediate

Q63: Draw a network of any size that

Q65: A backward pass is performed when it

Q65: What is the late start time for

Q67: An activity has an optimistic time estimate

Q69: A project has the precedence requirements and

Q71: Project Test Bank is composed of activities

Q72: What is the slack time for Activity

Q81: In assigning a value for the most

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines