menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    Use the Network Diagram and Activity Lengths in the Nodes
Solved

Use the Network Diagram and Activity Lengths in the Nodes

Question 93

Question 93

Multiple Choice

Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.   A)  26 B)  25 C)  24 D)  23


A) 26
B) 25
C) 24
D) 23

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: A merge activity has two or more

Q64: _ is the identification of the project

Q88: Based on the activity network pictured, what

Q89: Discuss any five approaches to reducing the

Q89: Use the information in the table to

Q89: The length of time expected to complete

Q92: What is the earliest that Activity D

Q96: Consider a project composed activities X and

Q97: A project has the precedence requirements and

Q98: Use the values in the table to

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines